Construction of Coal Rail Corridor By Mahanadi Coal Railway Limited

Published on

New Delhi: Coal Rail Corridor By Mahanadi Coal Railway Limited: Inner Rail Corridor for a length of 68 km. is being constructed by Mahanadi Coal Railway Limited (MCRL) in two phases. Phase-I is Angul-Balram Rail Link which is 14 KM length and Phase-ll is Balram-Putugadia-Jarapada-Tentuloi Rail Link length is 54 KM.

This information was given by the Union Minister of Coal, Mines and Parliamentary Affairs Shri Pralhad Joshi in a written reply in Rajya Sabha today. The status of physical progress of Phase-I is construction of the entire 14 KM is in an advance stage by IRCON. Physical progress -95%. Scheduled Commissioning by IRCON: 31.07.22.

where as Phase-II on land acquisition is under process by IRCON. Phase-I 14 km of all the land acquisition process has been completed including forestry clearance. Phase II- 54 km of land acquisition is being done under Railway Amendment Act 2008. E-gazette notification under Section 20A (i) for tenancy and Govt. Non-Forest land has been published on 10.06.2022. Stage-I forest clearance has been obtained on 03.12.2021. Compliance to observation for Stage-II clearance has also been submitted. Site specification wild life management plan has also been approved by Principal Conservator of Forest (Wild life), Bhubaneswar on 21.06.2022.

This project is intended to provide common rail corridor for evacuation of coal from both CIL and non-CIL coal blocks in Talcher Coal Field Area. This project will also provide multiple entries and exit points for coal rakes for faster evacuation of coal and de-congest the Indian Railway system by avoiding concentration of rakes at limited entry and exit route from Talcher Coal Field.

Government is planning to produce coal from Talcher area by 2030, as per the details given below:-

CIL coal blocks – 182.29 MT

Non-CIL coal blocks – 87.50 MT

Read Also | Home Minister Amit Shah greets people on National Handloom Day

[amazon_auto_links id=”635″]

(adsbygoogle = window.adsbygoogle || []).push({});

Share Market

Bitcoin Vs Gold Vs Nifty 50: Which Investment Delivered The Best 5-Year Returns?

Compare Bitcoin, gold and Nifty 50 five-year returns and understand their risks before deciding where to invest in 2026.

Stock Market Holiday Today: NSE, BSE Closed on October 20 for Dussehra

Indian stock markets are closed on October 20 for Dussehra. Check NSE, BSE, MCX trading hours, bank holidays and the next market session.

More like this

Cyclone Arnab: Red Alert Issued For Six Districts, Odisha CM Reviews Preparedness, Fishermen Warned

Cyclone Arnab alert in Odisha: Red warnings issued for vulnerable districts as heavy rain threatens. Fishermen advised to stay away from the sea.

PM Modi to Inaugurate RBI Data Centre in Bhubaneswar on October 25

PM Modi will inaugurate an RBI data centre and cybersecurity institute in Bhubaneswar on October 25, alongside a garment facility launch in Varanasi.

India Beat New Zealand by Four Wickets in 2nd T20I, Take 2-0 Series Lead

India beat New Zealand by four wickets in the second T20I as Tilak Varma scored 51 and Naman Dhir helped seal the chase of 181.